You signed in with another tab or window. Reload to refresh your session.You signed out in another tab or window. Reload to refresh your session.You switched accounts on another tab or window. Reload to refresh your session.Dismiss alert
{{ message }}
Repository navigation
Bounded shutdown grace and recovery when the stopped receipt is missing #264
If the host process is killed during a provider session before the stopped audit receipt is written, the job stays leased and the auth fenced, and RecoverStoppedProvider (#251) refuses because the receipt is required evidence. The controller then admits nothing further for that job. There is also no bounded shutdown grace that would let the guest return auth before Close stops the unit.
Acceptance criteria
Close waits a bounded, documented grace for an in-flight native session to return auth and write its stopped receipt before stopping the unit; the bound is tested and never extends indefinitely.
Needs an owner decision before implementation: whether a lease whose stopped receipt is missing may ever be recovered, and on what alternative evidence (for example a fresh whole-unit stop proof plus retiring the auth unconditionally). Until decided, that case stays fenced as today.
Validation
go -C reviewer test -race ./...; an E2E case killing the host process mid-session (once the decision is recorded).
The bounded shutdown grace and the session budget rule merged in #272 (6a0d717). Still open: recovering a lease whose stopped receipt is missing, which waits on the owner decision recorded above. Lost E2E coverage of the fenced branch is tracked in #271.
Closed per Franz (2026-10-29 19:34 ET, set-it-free-loop post: 'Agreed'): SFL stays inside pmd (project-manager). The standalone alpha controller, adapters and publisher are not being built. Next SFL work is project-manager #75 (review status) and #76 (changes between rounds). Reopen if that direction changes.
Activity
Give an exported provider session a bounded shutdown grace and end un…
HemSoft commentedon Oct 24, 2026
The bounded shutdown grace and the session budget rule merged in #272 (6a0d717). Still open: recovering a lease whose stopped receipt is missing, which waits on the owner decision recorded above. Lost E2E coverage of the fenced branch is tracked in #271.
Reach the fenced provider-close branch in E2E again with close-provid…
HemSoft commentedon Oct 28, 2026
Park with its worker; no credential recovery or policy decision is implied. The native-review plan does not run the local worker.
The parked work stops. Revival requires the original unresolved gates, as stated in the approved plan.
HemSoft commentedon Oct 29, 2026
Closed per Franz (2026-10-29 19:34 ET, set-it-free-loop post: 'Agreed'): SFL stays inside pmd (project-manager). The standalone alpha controller, adapters and publisher are not being built. Next SFL work is project-manager #75 (review status) and #76 (changes between rounds). Reopen if that direction changes.