Ops requirements needed for production rollout of Durable Sync. #15
We need some details around what's needed from an Ops perspective to feel comfortable going from Phase 1 to Phase 2 here in the plan to roll out Durable Sync for new users only.
So we can get some more accurate timelines attached to the above plan, can you provide us with details around what you need in order to feel comfortable routing 10% of new users to Spanner?
As far as details around our timeline...we'd like to get to Phase 2 before the end of the year.
Operations requirements for taking 10% of production users.
QA sign-off on supported Sync clients interactions with Sync-RS.
QA sign-off on server component with particular emphasis on load testing.
Operational readiness:
Add Sync-RS monitoring.
Review of __heartbeat__ endpoint.
Basic service documentation, this exists but should be updated.
Description of operational level agreement:
How slow is too slow? As measured by average upstream_response time, or network time?
What is the errors per second threshold before considering the service broken?
Uptime requirements: If GCPs Spanner service is down for > X minutes, we're down.
Any other availability or performance requirements.
A documented understanding that this phase of rollout is a live operational acceptance test.
Taking care to make a use vs. mention distinction, this service while named "durable sync" is not yet proven durable, and Operations is, for the purposes of this test, going to consider Sync-RS equivalent to the non-durable sync nodes and use the same toolset, including the data loss inducing user migrations, to deal with encountered problems.
Thank you so much for the details here, @Micheletto, this is incredibly helpful. I'm going to close this out and we can shift over to linked tasks from here.
Operations requirements for taking 10% of production users.
QA here is underway. I'll leave monitoring to you (unless there's anything else you need from us there, in which case let me know).
With regards to the heartbeat endpoint, I've opened this issue which we'll tackle next week.
With regards to the operational agreement, I'll take a stab at it next week: I opened this issue to track status there.
In terms of documenting expectations around "durability", I've added a final new "graduating to durable status" item to our rollout plan and will not plan on referring externally to Sync as "durable" until that happens.
Operations requirements to graduating service to durable status:
Thanks for this bit as well. Since we're looking at ~3 months until we get to this stage, I'm going to hold off on creating specific tasks here. As we get closer, we'll revisit it, and this won't be lost as it's clearly linked in the last phase of the plan to enable for new Sync users.
Activity
Micheletto commentedon Nov 14, 2019
Operations requirements for taking 10% of production users.
Micheletto commentedon Nov 14, 2019
Operations requirements to graduating service to durable status:
tublitzed commentedon Nov 15, 2019
Thank you so much for the details here, @Micheletto, this is incredibly helpful. I'm going to close this out and we can shift over to linked tasks from here.
QA here is underway. I'll leave monitoring to you (unless there's anything else you need from us there, in which case let me know).
With regards to the heartbeat endpoint, I've opened this issue which we'll tackle next week.
With regards to the operational agreement, I'll take a stab at it next week: I opened this issue to track status there.
In terms of documenting expectations around "durability", I've added a final new "graduating to durable status" item to our rollout plan and will not plan on referring externally to Sync as "durable" until that happens.
Thanks for this bit as well. Since we're looking at ~3 months until we get to this stage, I'm going to hold off on creating specific tasks here. As we get closer, we'll revisit it, and this won't be lost as it's clearly linked in the last phase of the plan to enable for new Sync users.